MARSA BAY — PKG-2 - Daily Progress Report - 2026-06-02
Demo data — fictional (Marsa Bay dummy-pack). Auto-drafted by Prensia; awaiting PM sign-off. Updated 3×/day.
A. HEADER / COVER
ProjectMARSA BAY — PKG-2 (Oil & Gas / Petrochem EPC)
Report NoDR-2026-06-02
Date2026-06-02 (Tuesday)
Working hoursDay shift (night not reported)
Main ContractorMeridian EPC
Owner / PMTMBP (Company: Owner / MBP)
Prepared byPrensia - Project Controls Agent
Reviewed / Approved byPM (signature below)
DistributionPMT, Main Contractor, Subcontractors
Previous reportDR-2026-06-01
B. WEATHER
Not reported today.
C. EXECUTIVE NARRATIVE
Manpower was 1,835 (down from 1,860) with 16 cranes held. The dominant item today was readiness for a Owner (Marsa Bay Petrochemicals) site walkthrough tomorrow, 03 June at 09:00, flagged from the weekly Quality Meeting; named areas of concern are process piping, controlled excavation / re-excavation, equipment preservation compliance, E&I cables, equipment and the substation. Construction leaders were asked to prepare. Separately, the C-110 tailing-crane area needs urgent leveling and compaction. The Meridian head-count was again issued as an Excel sheet.
D. MANPOWER
| Source |
Headcount |
Cranes |
Remarks |
| Meridian Head Count (Excel) |
1,835 |
16 |
Posted with .xlsx attachment |
| Total on site |
1,835 |
16 |
-27 vs 01 Jun; cranes steady |
E. EQUIPMENT & RESOURCES
| Equipment |
Working |
Idle |
Idle cause |
Remarks |
| Cranes |
16 |
Not reported |
- |
Incl. C-110 tailing crane (area prep needed) |
F. WORK PERFORMED TODAY
| Unit / Area |
Discipline |
Activity |
Status / Progress |
Remarks |
| Area-60 (C-110) |
Civil |
Tailing-crane area leveling & compaction |
Requested - urgent |
Crane positioning prerequisite |
| Project-wide |
QA/QC |
Prep for Company site walkthrough (03 Jun) |
In progress |
Leaders mobilising on areas of concern |
G. CONCRETE POURS LOG
| Type |
Tag / Location |
Qty (m3) |
Remarks |
| Completed |
None reported today |
- |
No pour volumes posted |
| Planned / balance |
None reported today |
- |
- |
H. MATERIALS & DELIVERIES
None reported today. (The daily Meridian head-count Excel is a manpower/equipment sheet - not a material delivery; see Manpower.)
I. INSPECTIONS, RFI & QC/NCR
| Item |
Location |
Status |
Owner / Party |
Remarks |
| Owner (Marsa Bay Petrochemicals) site walkthrough |
Project-wide |
Scheduled 03 Jun 09:00 |
All construction leaders |
Concerns: process piping, controlled excavation/re-excavation, equipment preservation, E&I cables, equipment, substation |
J. SAFETY (HSE)
No incidents reported.
K. DELAYS & DISRUPTIONS
| Cause |
Impact |
Responsible party |
Claims / EOT note |
Remarks |
| C-110 tailing-crane area not level/compacted |
Crane positioning held until area prepared |
Civil / earthworks |
Internal |
Marked urgent |
L. OPEN ISSUES & ACTIONS
| # |
Issue |
Owner / Action |
Party |
Priority |
Status |
| 1 |
C-110 tailing-crane area leveling & compaction |
Arrange urgently |
Civil / earthworks |
High |
Open |
| 2 |
Company walkthrough readiness (process piping, excavation, preservation, E&I, substation) |
Prepare each area |
All leaders |
High |
Open - due 03 Jun |
| 3 |
U-30 sub-area B CLD formwork (from 01 Jun) |
Expedite |
Delta Civil (sub) |
High |
Carry-forward |
Look-ahead — planned for tomorrow
- Owner (Marsa Bay Petrochemicals) site walkthrough at 09:00 - have process piping, controlled excavation/re-excavation, preservation, E&I cables, equipment and substation presentable.
- Complete leveling & compaction of the C-110 tailing-crane area.
Insights
- Tomorrow is an external audit, not a normal day. A Owner (Marsa Bay Petrochemicals) walkthrough with a named concern list is a graded event - anything not closed by 09:00 03 Jun becomes a visible finding. The six concern areas should each have an owner tonight.
- Preparation vs. production trade-off: expect some manpower to shift from production to walkthrough prep tomorrow; the slight headcount dip (1,860 -> 1,835) may continue. That is acceptable if it buys a clean audit.
- C-110 is on the critical path for lifting - the crane cannot set up until the area is leveled/compacted, so the "urgent" tag is justified; treat as today's top civil action.
- Forward reminders: (1) 03 Jun 09:00 - Company site walkthrough (process piping / excavation / preservation / E&I / equipment / substation). (2) C-110 area prep before the walkthrough. (3) U-30 CLD formwork still open from 01 Jun.
Lessons learned
- Name an owner for every concern area the night before an Owner walkthrough — anything left open at audit time becomes a visible finding.
- Crane set-up sits on civil area-prep; treat leveling/compaction of a crane area as the gating, critical-path action, not routine earthworks.
N. TRENDS & CHARTS
Manpower trend chart (10-day window ending 2026-06-02) is rendered above. No pour volumes posted today, so the pours chart is not shown.
O. PHOTOS / ATTACHMENTS
- C-110 tailing-crane area - leveling/compaction needed (photo).
- Meridian Head Count Manpower Equipment - 2 June 2026 (Excel attachment).
(Synced photos appear in the gallery above this report.)