MARSA BAY — PKG-2 - Daily Progress Report - 2026-06-02

Demo data — fictional (Marsa Bay dummy-pack). Auto-drafted by Prensia; awaiting PM sign-off. Updated 3×/day.

A. HEADER / COVER

ProjectMARSA BAY — PKG-2 (Oil & Gas / Petrochem EPC)
Report NoDR-2026-06-02
Date2026-06-02 (Tuesday)
Working hoursDay shift (night not reported)
Main ContractorMeridian EPC
Owner / PMTMBP (Company: Owner / MBP)
Prepared byPrensia - Project Controls Agent
Reviewed / Approved byPM (signature below)
DistributionPMT, Main Contractor, Subcontractors
Previous reportDR-2026-06-01

B. WEATHER

Not reported today.

C. EXECUTIVE NARRATIVE

Manpower was 1,835 (down from 1,860) with 16 cranes held. The dominant item today was readiness for a Owner (Marsa Bay Petrochemicals) site walkthrough tomorrow, 03 June at 09:00, flagged from the weekly Quality Meeting; named areas of concern are process piping, controlled excavation / re-excavation, equipment preservation compliance, E&I cables, equipment and the substation. Construction leaders were asked to prepare. Separately, the C-110 tailing-crane area needs urgent leveling and compaction. The Meridian head-count was again issued as an Excel sheet.

D. MANPOWER

Source Headcount Cranes Remarks
Meridian Head Count (Excel) 1,835 16 Posted with .xlsx attachment
Total on site 1,835 16 -27 vs 01 Jun; cranes steady

E. EQUIPMENT & RESOURCES

Equipment Working Idle Idle cause Remarks
Cranes 16 Not reported - Incl. C-110 tailing crane (area prep needed)

F. WORK PERFORMED TODAY

Unit / Area Discipline Activity Status / Progress Remarks
Area-60 (C-110) Civil Tailing-crane area leveling & compaction Requested - urgent Crane positioning prerequisite
Project-wide QA/QC Prep for Company site walkthrough (03 Jun) In progress Leaders mobilising on areas of concern

G. CONCRETE POURS LOG

Type Tag / Location Qty (m3) Remarks
Completed None reported today - No pour volumes posted
Planned / balance None reported today - -

H. MATERIALS & DELIVERIES

None reported today. (The daily Meridian head-count Excel is a manpower/equipment sheet - not a material delivery; see Manpower.)

I. INSPECTIONS, RFI & QC/NCR

Item Location Status Owner / Party Remarks
Owner (Marsa Bay Petrochemicals) site walkthrough Project-wide Scheduled 03 Jun 09:00 All construction leaders Concerns: process piping, controlled excavation/re-excavation, equipment preservation, E&I cables, equipment, substation

J. SAFETY (HSE)

No incidents reported.

K. DELAYS & DISRUPTIONS

Cause Impact Responsible party Claims / EOT note Remarks
C-110 tailing-crane area not level/compacted Crane positioning held until area prepared Civil / earthworks Internal Marked urgent

L. OPEN ISSUES & ACTIONS

# Issue Owner / Action Party Priority Status
1 C-110 tailing-crane area leveling & compaction Arrange urgently Civil / earthworks High Open
2 Company walkthrough readiness (process piping, excavation, preservation, E&I, substation) Prepare each area All leaders High Open - due 03 Jun
3 U-30 sub-area B CLD formwork (from 01 Jun) Expedite Delta Civil (sub) High Carry-forward

Look-ahead — planned for tomorrow

  • Owner (Marsa Bay Petrochemicals) site walkthrough at 09:00 - have process piping, controlled excavation/re-excavation, preservation, E&I cables, equipment and substation presentable.
  • Complete leveling & compaction of the C-110 tailing-crane area.

Insights

  • Tomorrow is an external audit, not a normal day. A Owner (Marsa Bay Petrochemicals) walkthrough with a named concern list is a graded event - anything not closed by 09:00 03 Jun becomes a visible finding. The six concern areas should each have an owner tonight.
  • Preparation vs. production trade-off: expect some manpower to shift from production to walkthrough prep tomorrow; the slight headcount dip (1,860 -> 1,835) may continue. That is acceptable if it buys a clean audit.
  • C-110 is on the critical path for lifting - the crane cannot set up until the area is leveled/compacted, so the "urgent" tag is justified; treat as today's top civil action.
  • Forward reminders: (1) 03 Jun 09:00 - Company site walkthrough (process piping / excavation / preservation / E&I / equipment / substation). (2) C-110 area prep before the walkthrough. (3) U-30 CLD formwork still open from 01 Jun.

Lessons learned

  • Name an owner for every concern area the night before an Owner walkthrough — anything left open at audit time becomes a visible finding.
  • Crane set-up sits on civil area-prep; treat leveling/compaction of a crane area as the gating, critical-path action, not routine earthworks.

N. TRENDS & CHARTS

Manpower trend chart (10-day window ending 2026-06-02) is rendered above. No pour volumes posted today, so the pours chart is not shown.

O. PHOTOS / ATTACHMENTS

  • C-110 tailing-crane area - leveling/compaction needed (photo).
  • Meridian Head Count Manpower Equipment - 2 June 2026 (Excel attachment). (Synced photos appear in the gallery above this report.)

Approval & Sign-off

Reviewed / Approved by
Not yet signed — use the Signature panel →
PENDING APPROVAL
upload a photo/scan of the PM signature