Marsa Bay — PKG-2Project dashboard · daily record · 03 Jun 2026 Manpower today
1,896
+61 vs yesterday
Cranes
16
heavy-lift steady
Concrete today
64 m³
STR-200 beams
Safety events
0
no incidents
Manpower trend (3 days)
Open issues by responsible party
Owner / Meridian HSE1
Delta Civil (sub)1
Main contractor1
Open issues & actions
| Area | Issue | Party | Priority |
|---|
| U-50 | Permit hold (all permits) | Meridian HSE | High |
| STR-200 | Confirm beam pour 64 m³ | Meridian / Delta | Med |
| U-30 sub-area B | CLD formwork (open ~2d) | Delta Civil | High |
Look-ahead — planned for tomorrow
- Clear the U-50 permit hold and resume works
- Confirm STR-200 beam-pour completion + volume
- Action any Owner-walkthrough findings
- Progress U-30 sub-area B CLD formwork